In a project that underscored agility and responsiveness, Rapid Readymix delivered concrete for a residential extension in Wandsworth, employing a volumetric mixer and line pump. Building on a positive previous experience with us in 2021 for a garden room slab, the customer re-engaged our services for their house extension, highlighting the trust and satisfaction in our concrete delivery solutions.
Job Background
Returning to a familiar site, the task was to supply 9m3 of C25 concrete for foundation work as part of a residential extension. Scheduled for a Saturday morning, the delivery was critical for the project’s next phase. Our prior engagement had set a precedent for quality and service, leading the customer to once again choose Rapid Readymix for their concrete needs.
Job Requirements
The job required precise coordination and timing, delivering 9m3 of C25 concrete to meet the foundational needs of the residential extension. The choice of a Saturday morning for delivery underscored the importance of flexibility in our operations, catering to the customer’s schedule to ensure the project stayed on track.
Constraints and Challenges
Unexpected challenges arose following heavy rainfall the day before delivery. Part of the footings had collapsed overnight, necessitating more concrete than initially ordered. Moreover, the partial collapse left an existing wall unsupported, escalating the urgency to fill the foundations promptly. Compounded by a fully booked schedule, the sudden need for additional concrete put our capacity and responsiveness to the test.
Techniques and Hardware Used
In response to the unforeseen demand for extra concrete, Rapid Readymix leveraged our Aggsmart shipping system. This technology enabled real-time tracking of our fleet, identifying a volumetric mixer close by with a sufficient part-load immediately after completing another delivery. A new route was issued to the driver’s sat-nav, ensuring the swift arrival of the second mixer to the site.
Conclusion
The quick thinking and efficient use of our Aggsmart system allowed us to address the sudden increase in concrete demand, demonstrating our commitment to customer service and our ability to adapt to challenges. The successful delivery of the additional concrete mitigated the risk to the property and alleviated the customer’s concerns, ensuring the foundation work could proceed without further delays. The customer’s expression of relief and gratitude reaffirms our role not just as a supplier but as a reliable partner in our clients’ construction endeavours. This case study exemplifies Rapid Readymix’s dedication to meeting the demands of domestic and commercial projects in the Greater London and Surrey areas, even under unexpected and challenging circumstances.