Introduction

Rapid Readymix undertook a project located in Hampstead, NW3, focused on constructing a basement and exterior slab. The project entailed the delivery of readymix concrete in large quantities. To facilitate efficiency, a concrete pump with a 30m line was used to transport the material directly to the construction site.

Background

The project site had received over 80 cubic metres of concrete in previous deliveries, and the work is still ongoing. One of the critical aspects of the project was ensuring the consistent turnaround of trucks, especially during larger pours. To achieve this, multiple trucks were dispatched, each released 20 minutes apart. This strategy was necessary due to the site’s location and traffic conditions.

The primary objective of this project was the construction of a basement, which required the use of specialised concrete mixes.

Readymix Concrete in Hampstead full view

Project Objectives and Requirements

36 cubic metres of concrete were ordered, and the final amount actually required was 33.75 cubic metres. Masterpel waterproofer additive was also included in the mix design to ensure the longevity and durability of the basement structure.

The use of a pump for the delivery proved to be highly efficient, with the on-site duration from the first mixer’s arrival to the last one’s departure being only 2 hours and 9 minutes.

Challenges

One of the anticipated issues was access restrictions, but this was mitigated by thorough preparation and ensuring all drivers were familiar with the site setup.

To efficiently navigate the traffic and ensure the timely delivery of materials, it was necessary to use our AGGSMART traffic monitoring and GPS technology to monitor and manage routes. This was important for maintaining project schedules and minimising delays.

Solutions

Rapid Readymix employed a concrete pump to ensure a fast and clean delivery of the readymix concrete. This hardware was pivotal in maintaining efficiency during the construction process.

Additionally, Rapid Readymix made use of AggSmart technology to constantly monitor traffic conditions. This allowed the company to divert trucks away from traffic build-ups and ensure their swift arrival at the construction site.

Results and Conclusion

The use of specialised tools and proactive management techniques resulted in an expedited and efficient concrete delivery process. The tasks were completed in a timely manner with a very brief on-site duration.

The client benefited from Rapid Readymix’s efficient planning and execution, which played a significant role in the successful construction of the basement.

This project showcases Rapid Readymix’s capability in effectively managing logistics and utilising specialised equipment to ensure efficient and timely delivery of readymix concrete for construction projects.

Efficient Concrete Delivery From Rapid Readymix

Discover how Rapid Readymix can optimise your construction process with efficient concrete delivery solutions. Get in touch with us for more information and let us assist in bringing your construction project to a successful completion.